The challenge
A dual-brand hotel requires close coordination between plans, specifications, and the requirements of each flag. Purchasing against documents without reconciling their differences can carry a discrepancy directly into an order.
The review
JSM brought a design-informed lens to the purchasing review, checking plans, specifications, and brand requirements together. That review identified more than $100,000 in potential errors, including an approximately $80,000 issue involving vanity scaling and tagging.
The result
The discrepancies were identified before ordering, and marked-up documents were returned for correction. The value was in recognizing the problem while it could still be addressed in the documentation, before it became a purchasing or installation issue.